Shillong, Nov 26: The Ministry of Minority Affairs has asked North-Eastern Hill University (NEHU) to start work on the PMJVK projects at its Tura Campus within 30 days or refund the Rs 45 crore already released.
The direction was given in a letter dated November 19, 2026, from the Ministry to NEHU.
The projects, a 700-capacity auditorium, a boys’ hostel and a girls’ hostel, were sanctioned under the Pradhan Mantri Jan Vikas Karyakram (PMJVK) at a total cost of Rs 92.31 crore.
The Ministry released Rs 45 crore in June-July 2025 (Rs 30 crore for the auditorium, Rs 6 crore for the boys’ hostel and Rs 9 crore for the girls’ hostel). However, work has not commenced.
In its letter, the Ministry flagged “possible procedural irregularities” in the change of executing agency. It said NEHU had initially decided to execute the works through the Meghalaya Tourism Development Corporation (MTDC), but later changed the agency to CPWD without prior intimation and without terminating the MoU with MTDC.
The Ministry has directed NEHU to commence work through MTDC within 30 days, in consultation with the State government, failing which the released amount is to be refunded immediately.
The issue was raised in a memorandum submitted to Union Minister for Minority Affairs Kiren Rijiju by Tony Tojrang B. Marak.
In his memorandum, Marak said the funds have been lying unutilised for over a year while students at Tura Campus continue to suffer for want of hostel and auditorium facilities.
He alleged that NEHU unilaterally changed the agency from MTDC to CPWD without terminating the MoU and without informing the Ministry, causing the delay.
Marak said MTDC is ready to commence work and land is available at the campus. He apprehended that the funds may lapse or be diverted if work is not started immediately, and urged the Minister to direct NEHU to start work, investigate the alleged irregularities and fix accountability.